NOTICE: Colony Construction, Inc. will be milling and paving Graham Rd. from S. Crater Rd. to S. Sycamore St.
Schedule is as follows:
- Begin mill and pave at S. Crater Rd. with a detour for westbound traffic. Detour in place Nov. 16 - Nov. 19 from 9:00 am - 4:30 pm.
- Mill and pave from I-95 off-ramp to S. Sycamore St. Nov. 19 - Nov. 30 from 8:00 am - 5:00 pm.
- No work Nov. 25 - Nov. 29.
Photo: Map showing the detour.